Harbour Shed Repairs

1491941 orig
Published 12:57 on 20 Aug 2024

Work on Harbour Shed:  Intona will commence work on the North elevation of the Harbour Shed from Friday 6 September when scaffolding will be erected.  On Monday 9 September work will continue by removing original gutters/down pipes and metal sheeting.  These will be replaced with new deep flow gutters and marine plywood with paper overlay/UPVC lining boards roof panels.  It is anticipated that work will be completed within 10 days.  Thanks to Harbour Shed users for their co-operation while work is being completed.